Wayne Farms Poultry Processing Company came to TOLM to design and build a new 5-million-gallon
sludge containment lagoon and integrate it into their existing Wastewater Treatment facility in their Danville, AR. Plant. This included using a location of an existing, unlevelled cattle grazing field with questionable soils, Relocation of existing high voltage power lines by ENTERGY, maintaining and complying with Wayne Farms high standards of Contractor Site Safety, tying into multiple Plant structures, and piping and providing for a sludge processing system that will effectively service the Plant’s needs for the foreseeable future.
Despite COVID-related delivery delays, TOLM Group worked with the client to mobilize a bypass pumping solution until the actual pump arrived. Never slowing down the project for the owner.